BURNSTONE MINE | MPUMALANGA – SOUTH AFRICA
Challenge – To do cost effective aerial support in main access decline from surface. Ground conditions deteriorated due to oxidation and weathering. After careful consideration management decided to use V-Seal Rock Liner TSL to “lock” in “Key Blocks” and give the required aerial support.
Project Gallery
A Glimpse Into Operations
Burnstone-Project | The CAA 32 Continuous Air Operated pump
The CAA 32 Continuous Air Operated pump that mix and spray the V-Seal continuously. This pump is capable to spray up to 50 square metres at a thickness of 8-10 mm per hour. Very user friendly, easy to clean and maintain and most of all, very cost effective. Components easily removed and replaced in case of a breakdown. If the pumps are properly flushed and cleaned after use, they give many months of trouble-free service.
Burnstone-Project | Access Decline
As can be seen in these pictures, the side and hanging walls deteriorated considerably due to weathering and oxidation, and is not safe to re-drill to support with tendons and wire mesh.
Carbontech-Burnstone-Project (16)
As can be seen in these pictures, the side and hanging walls deteriorated considerably due to weathering and oxidation, and is not safe to re-drill to support with tendons and wire mesh.
Burnstone-Project-Mpumalanga
Challenge – To do cost effective aerial support in main access decline from surface. Ground conditions deteriorated due to oxidation and weathering. After careful consideration management decided to use V-Seal Rock Liner TSL to “lock” in “Key Blocks” and give the required aerial support.
Burnstone-Project | Access Decline
As can be seen in these pictures, the side and hanging walls deteriorated considerably due to weathering and oxidation, and is not safe to re-drill to support with tendons and wire mesh.
Burnstone-project | spraying v-seal with 1.5 m nozzle
V-Seal sprayed onto the sidewalls utilising the 1,5 metre spray nozzle. This nozzle will effectively spray areas up to 4m high.
Burnstone-Project | Rock covered with the high strength flexible v-seal rock liner
The area in the Decline is covered with a 10mm layer of V-Seal. Note the probing thickness measuring done at regular intervals to ensure proper coverage.
Burnstone-Project | Rock covered with the high strength flexible v-seal rock liner
The area in the Decline is covered with a 10mm layer of V-Seal. Note the probing thickness measuring done at regular intervals to ensure proper coverage.